Buy America requirements for Arkansas infrastructure projects
Federal funds that reach Arkansas projects through the State Revolving Funds, BEAD and the federal-aid highway program carry domestic-content requirements. The rules differ by program; here is who administers each one and what applies.
Water and wastewater (SRF)
Clean Water SRF: Arkansas Department of Agriculture
- Build America, Buy America under 2 CFR Part 184 for iron and steel, manufactured products and construction materials.
- American Iron and Steel (AIS) also applies to SRF-assisted projects.
- EPA's de minimis waiver: up to 5% of total project cost, cumulative, with no dollar cap.
Broadband (BEAD)
State broadband office: ARConnect: The Arkansas State Broadband Office
- Build America, Buy America under 2 CFR Part 184, with fiber optic cable and optical fiber treated as construction materials (184.6(a)(4)–(5)).
- NTIA's BEAD waiver exempts some equipment under conditions; the state office's guidance controls how it applies.
- De minimis: the lesser of $1,000,000 or 5% of applicable costs, as described in state BEAD guidance. Confirm against NTIA's current waiver.
Federal-aid highways
State DOT: Arkansas Department of Transportation
- Iron and steel: every manufacturing process, including coating, in the U.S. (23 CFR 635.410(b)(1)). Foreign iron and steel is limited to the greater of 0.1% of contract cost or $2,500.
- Manufactured products: for projects obligated on or after October 1, 2025, manufactured in the U.S.; from October 1, 2026, also more than 55% U.S. component cost (23 CFR 635.410(c)).
- Construction materials follow 2 CFR 184.6; the USDOT de minimis waiver allows the lesser of $1,000,000 or 5% of applicable material cost.
What a Arkansas Buy America submittal should include
- A manufacturer's certification naming the project and contract, the product, where it was made and which requirement it meets, signed by an authorized representative. Some Arkansas programs publish their own form; use it when they do.
- For iron and steel: mill test reports for every heat delivered, showing U.S. melt and pour.
- For manufactured products: the component-cost calculation behind the domestic-content percentage.
- For construction materials: confirmation that each listed process for that material happened in the U.S.
- A record of anything accepted under a waiver, and how much of the project's allowance it used. The waiver calculator works it out.
SubmittalForge checks these documents against each other and against the rule for the project's funding agency. Check a mill test report or see a sample project review.