BABA waiver allowance calculator
How much non-compliant iron, steel and manufactured product a federally funded project can absorb under its agency's de minimis, minimal-use and small-grant waivers, and how much is left.
1. The project
2. Material that isn't compliant
Each item that doesn't meet Buy America, at its cost as delivered to the project: steel melted abroad, a manufactured product under the domestic-content threshold, and so on.
Choose the funding agency to start
Each agency sizes its waivers differently: EPA on the total project cost, FHWA on the contract and the cost of materials. Only the figures your agency uses are asked for.
Track it as submittals come in
In a project, the waiver ledger adds up non-compliant material from the mill certs automatically, and everyone you share the project with sees it. On GC & Engineer, with a 14-day free trial.
Start freeWhat the waivers allow
Build America, Buy America (2 CFR Part 184) requires iron, steel, manufactured products and construction materials on federally funded infrastructure to be produced in the United States. Agencies have issued general waivers that let a small share of a project's material fall short: a de minimis allowance sized on the project's costs, a minimal-use allowance for small amounts of iron and steel, and a small-grant waiver for low-value awards. Anything over them needs a project-specific waiver under 2 CFR 184.7, or replacement material.
Allowances by agency
| Agency | General waivers |
|---|---|
| EPA Clean Water / Drinking Water SRF | EPA de minimis waiver: 5% of total project cost |
| DOT / FHWA Federal-aid highway | FHWA iron & steel minimal use: 0.1% of total contract cost, at least $2,500De minimis waiver: 5% of cost of covered materials, up to $1,000,000Small-grant waiver: awards below $500,000 in federal assistance |
| DOT / FTA transit | De minimis waiver: 5% of cost of covered materials, up to $1,000,000 (terms unconfirmed) |
| NTIA BEAD broadband | De minimis waiver: 5% of cost of covered materials, up to $1,000,000 (terms unconfirmed) |
| HUD | De minimis waiver: 5% of cost of covered materials, up to $1,000,000Small-grant waiver: awards at or below $350,000 in federal assistance |
| FEMA | De minimis waiver: 5% of cost of covered materials, up to $1,000,000 (terms unconfirmed) |
| Department of Energy | No general de minimis waiver confirmed for DOE. Enter the allowance from your award terms, if any. |
| USDA Rural Utilities Service | No general de minimis waiver confirmed for USDA RUS. Enter the allowance from your award terms, if any. |
Waivers are granted by the agency, not by this calculator: confirm the terms that apply to your award with the contracting officer. To track the allowance across a whole project as submittals arrive, use the waiver ledger, which adds up non-compliant material from the mill certs. To check one mill cert, use the MTR validator.