BABA waiver allowance calculator

How much non-compliant iron, steel and manufactured product a federally funded project can absorb under its agency's de minimis, minimal-use and small-grant waivers, and how much is left.

1. The project

2. Material that isn't compliant

Each item that doesn't meet Buy America, at its cost as delivered to the project: steel melted abroad, a manufactured product under the domestic-content threshold, and so on.

Choose the funding agency to start

Each agency sizes its waivers differently: EPA on the total project cost, FHWA on the contract and the cost of materials. Only the figures your agency uses are asked for.

Track it as submittals come in

In a project, the waiver ledger adds up non-compliant material from the mill certs automatically, and everyone you share the project with sees it. On GC & Engineer, with a 14-day free trial.

Start free

What the waivers allow

Build America, Buy America (2 CFR Part 184) requires iron, steel, manufactured products and construction materials on federally funded infrastructure to be produced in the United States. Agencies have issued general waivers that let a small share of a project's material fall short: a de minimis allowance sized on the project's costs, a minimal-use allowance for small amounts of iron and steel, and a small-grant waiver for low-value awards. Anything over them needs a project-specific waiver under 2 CFR 184.7, or replacement material.

Allowances by agency

AgencyGeneral waivers
EPA Clean Water / Drinking Water SRFEPA de minimis waiver: 5% of total project cost
DOT / FHWA Federal-aid highwayFHWA iron & steel minimal use: 0.1% of total contract cost, at least $2,500De minimis waiver: 5% of cost of covered materials, up to $1,000,000Small-grant waiver: awards below $500,000 in federal assistance
DOT / FTA transitDe minimis waiver: 5% of cost of covered materials, up to $1,000,000 (terms unconfirmed)
NTIA BEAD broadbandDe minimis waiver: 5% of cost of covered materials, up to $1,000,000 (terms unconfirmed)
HUDDe minimis waiver: 5% of cost of covered materials, up to $1,000,000Small-grant waiver: awards at or below $350,000 in federal assistance
FEMADe minimis waiver: 5% of cost of covered materials, up to $1,000,000 (terms unconfirmed)
Department of EnergyNo general de minimis waiver confirmed for DOE. Enter the allowance from your award terms, if any.
USDA Rural Utilities ServiceNo general de minimis waiver confirmed for USDA RUS. Enter the allowance from your award terms, if any.

Waivers are granted by the agency, not by this calculator: confirm the terms that apply to your award with the contracting officer. To track the allowance across a whole project as submittals arrive, use the waiver ledger, which adds up non-compliant material from the mill certs. To check one mill cert, use the MTR validator.