Add mill test reports, bill of lading lines, BABA letter details and the spec requirement in the Documents dialog.

Everything the cross-check reads lives in a submittal's Documents dialog. Changes are saved only when you click Save, and the checks re-run straight away.

The quickest way: drop the files

  1. Open the project and pick the submittal in the register. A submittal with no documents shows Drop the documents here, or choose files.On Pro, GC & Engineer or a project pass. On Free, click Enter documents instead and type them in.
  2. Drop the packet, mill certs, bill of lading and BABA letter there (PDFs or photos, several at once), or click Choose files.
  3. Documents opens and reads each file twice. Pick the right value wherever the two readings disagree, check the rest, and click Save.

Or open the dialog

  1. Click Documents on the submittal.

Mill test reports

  1. On the Mill test reports tab, add each mill cert one of four ways:Enter a mill test report by hand and type the values from the report (every plan); Paste mill cert text and click Read and review to check what was read before adding it; Scan PDFs or photos → Choose files (Pro, GC & Engineer or a project pass); or pick one From your library.
  2. Click the pencil on a heat to see its values or correct them.Leave a box empty if the report doesn't state the value; it's flagged as not reported rather than guessed.
  3. Check the grade shown for each heat and change it in the dropdown if it was read wrong.A grade SubmittalForge doesn't check (anything other than A992, A36, A615 Grade 60, A53 Grade B, A500 Grade C and A312 TP316L) is kept as printed and marked limits not checked: origin and traceability are still checked, chemistry and tensile limits are not.
  4. Each heat shows Pass, Review or Fail against its grade.Remove a heat with the bin icon. On plans with the cert library, the bookmark icon saves the heat to it.
  5. Save keeps your changes. Closing the dialog with unsaved changes asks first.
  6. On paid plans and project passes, a file you scan is kept with the submittal when you save.Kept files are listed under Source files, below the submittal's details, where you can View or Download them. Keep a file stores another document without reading it, such as the signed BABA letter (PDF or image, up to 200 MB); to read a kept file into the submittal later, click Read into submittal next to it. View source on a mill test report opens the file at the page it was read from. Everyone with access to the project can open kept files; removing a file, clearing the documents or deleting the submittal deletes them. On the Free plan the values are saved but the file is not. Storage is 50 GB per organization on Subcontractor Pro, 250 GB on GC & Engineer, and 10 GB for a project on a project pass; remove files you no longer need to make room.

Bill of lading

  1. On the Bill of lading tab, enter the BOL / ticket no., Delivery date and Shipper / fabricator.
  2. Click Add line for each delivered item and fill in Piece marks, Description, Qty and Stamped heat.The stamped heat is what links a delivered piece to its mill cert.

BABA letter

  1. On the BABA letter tab, tick A manufacturer's Buy America certification is attached.Or click BABA letter on the submittal to draft one from its certs and attach it. See Generate a BABA certification letter.
  2. Enter the Contract no. on the letter, Signed by, and the Heat numbers on the letter (comma-separated).
  3. Tick each statement the letter actually makes: signed by an authorized representative, states which Buy America requirement it certifies, and (for coated products) that coating or galvanizing was done in the U.S.

Spec requirement

  1. On the Spec requirement tab, choose Use a saved requirement if the project has one for this section.Or set the CSI section and Required grade by hand. A new submittal starts with the grade Not set: the cross-check notes that instead of comparing grades, until you choose one.
  2. Untick Buy America applies to this submittal only if the award terms exclude it. The BABA letter and U.S. melt checks are then skipped and the cross-check says so.
  3. Tick Charpy V-notch testing required and enter the Minimum CVN (ft-lb) if the spec calls for it.
  4. Tick Hot-dip galvanizing required if it does.

Save

  1. You can also correct the Title, Subcontractor, Material cost (USD) and Buy America category at the top.
  2. Click Save. The register and score update.